We are promoting Third-Party Access to our gas infrastructure as part of our commitment towards supporting the opening up of the domestic gas market.
Should you have any questions or require any clarifications regarding EOI and ARF, please email to pgb.marketing@petronas.com
Access Arrangement:
Terminal Information Booklet:
Tariffs under the Third Party Access (TPA) System for:
- Peninsular Gas Utilisation (PGU)
- Regasificaton Terminal Sg Udang (RGTSU) in Melaka
- Regasification Terminal Pengerang (RGTP) in Johor
On 17 December 2025, the Government of Malaysia has approved the implementation of Regulatory Period 3 (“RP3”) under the Incentive Based Regulation (“IBR”) framework for the period effective from 1 January 2026 to 31 December 2028 for the gas facilities under PGB group of companies. The approved gas facility tariffs are as follows:
|
Gas Facilities
|
RP3 Base Tariffs
(1 January 2026 – 31 December 2028) |
Allowed Tariffs
(1 January 2026 - 31 December 2026) |
|---|---|---|
|
Peninsular Gas Utilisation (PGU)
Transportation tariff |
RM1.196/GJ/day
|
RM1.204/GJ/day
|
|
Compression tariff for the supply
of high-pressure gas to Singapore |
RM1.609/GJ/day
|
RM1.592/GJ/day
|
|
Regas Terminal Sungai Udang (RGTSU)
Regasification tariff |
RM3.542/GJ/day
|
RM3.540/GJ/day
|
|
Regas Terminal Pengerang (RGTP)
Regasification tariff |
RM3.142/GJ/day
|
RM3.103/GJ/day
|
Note: GJ indicates Giga Joule.
Allowed Tariffs reflect the tariff adjustments from annual review process, which intends to reflect changes in relation to reserved firm capacity and internal gas consumption as allowed under the IBR framework by Suruhanjaya Tenaga.
Please refer to the available firm capacity below:
PGU access to services application process flow:

Definition: Know-Your-Customer (KYC), Gas Transportation Agreement (GTA), Specific Terms and Conditions (STC), PGU Access Arrangement (PGU AA), Bank Guarantee (BG)
For further enquiry on our products and services, please contact us